Payment

Sl.no Description of work Payment in % No of days
1 Mobilization advance 13% 0
2 On completion of basement upto floor finish level 12% 20
3 Column raising up to ground roof level, electrical conduits in roofing and roof concreting 12% 20
4 Column rising up to First floor roof leve, electrical conduits in roofing and roof concreting 12% 20
5 Ground Floor Brick work upto roof level 7% 15
6 First Floor Brick work upto roof level 7% 15
7 Completion of parapet Wall 5% 5
8 Electrical conduits for ground floor, first floor box fixing and inner plastering 4% 5
9 All floor tiles and skirting laid 5% 15
10 Plumbing conduits for ground floor,first floor and wall, floor tile work complete 3% 5
11 All Floor wire pulling switch,socket,DB's LCB,MCB and all sanitanry fitting 2% 10
12 All Floor outside balcony and outside plastering work 5% 15
13 All floor doors shutter and window fixing 3% 5
14 Outside plumbing and sanitary lines work and outside painting one coat primer and one coat emulsion 3% 10
15 All floor inside putty one coat of primer and one coat of emulsion for all walls 2% 10
16 Finishing stage including final painting & polishing on wooden joineriers prior to handing over 2% 10
17 After completion and handing over 3%
Total 100% 180